Loading...
link : Mindef Mulls Delayed Littoral Combat Ships Project
Mindef Mulls Delayed Littoral Combat Ships Project
Loading...
04 Agustus 2020
Mindef consider three options for LCS : to be continued by Naval Group, to be continued by Boustead, or terminated the contract. Naval Group or Boustead to complete at least two LCS units (photo : Bernama)
KUALA LUMPUR -- The Ministry of Defence (Mindef) is considering three options in relation to the direction of the littoral combat ship (LCS) project, which has been been delayed, said its Minister Datuk Seri Ismail Sabri Yaacob.
He said that, as at July 31, none of the six LCS ships had been successfully completed by Boustead Naval Shipyard Sdn Bhd (BNSSB).
The overall work progress status of the project was 56.67 per cent compared to the original plan of 85.73 per cent, a delay of 31.1 months (29.06 per cent), he said.
Following that, a memorandum would be presented to the Cabinet after the ministry’s top management made a final review of the documents in the near future, he added.
“The first option is for the project to be continued by appointing Naval Group France as a rescue contractor through a Deed of Assignment with BNSSB using the remaining contract ceiling to complete at least two LCS units.
“As for the second option, the project is continued by BNSSB with the remaining contract ceiling to complete at least two LCS units,” he said while winding up the debate on the motion of thanks for the Yang di-Pertuan Agong's royal address for his ministry in the Dewan Rakyat, today.
Ismail Sabri said that the third option is the termination of the contract with BNSSB and the ministry starting efforts to save the project.
He said the ministry did not intend to inject additional funds to complete the LCS, instead BNSSB was asked to use the remaining allocation to continue the project.
“The government will not pay the debts acquired by BNSSB as requested by the company, however, the government will implement the payment to obtain the rights and complete the Detailed Design.
“Besides that, the government (will) make a claim for all the blocks and hulls of ships and LCS equipment purchased by BNSSB as the government has paid almost RM3 billion for this purpose,” he said.
He added that the current progress status for LCS 1 is at 59.79 per cent; LCS 2 (48.09 per cent); LCS 3 (43.75 per cent); LCS 4 (36.49 per cent) and LCS 5 (20 per cent) while LCS 6 has yet to start construction.
(Bernama)
thus Article Mindef Mulls Delayed Littoral Combat Ships Project
that is all articles Mindef Mulls Delayed Littoral Combat Ships Project This time, hopefully can provide benefits to all of you. Okay, see you in another article posting.
You now read the article Mindef Mulls Delayed Littoral Combat Ships Projectwith the link address https://uswordarmy.blogspot.com/2020/08/mindef-mulls-delayed-littoral-combat.html
Loading...
0 Response to "Mindef Mulls Delayed Littoral Combat Ships Project"
Post a Comment